LOW PRESSURE PNEUMATIC TEST | Prior to Hydraulic Testing
Pneumatic Pressure Testing, in this instance, is a non-destructive test used to prove the integrity of a pipework system or vessel before conducting a hydraulic … Read More
Pneumatic Pressure Testing, in this instance, is a non-destructive test used to prove the integrity of a pipework system or vessel before conducting a hydraulic … Read More
To ensure that any air handling unit [AHU] installed is maintained, operates efficiently, and is in line with the current design requirement years after installation, … Read More
An air handling unit consists of multiple components, with its main function being the primary piece of equipment within a ventilation system, to take recirculated … Read More
This air-cooled chiller checklist can be used and completed throughout the project and its different stages covering: Once the pre-functional checks have been completed, the … Read More
Upon completion of any new CRAC [computer room air conditioning] Unit installation or modifications to an existing unit, there will be a requirement to complete … Read More
Whether deploying a Hot Standby or Cold Standby strategy to condition a critical space, ‘Group Control’ will be used where multiple CRAH or CRAC Units … Read More
Upon completion of any new CRAH [computer room air handling] Unit installation or modifications to an existing unit, there will be a requirement to complete … Read More
The difference between a CRAC Unit System and a CRAH Unit System is how the heat is transferred and then removed/ejected from the system. A … Read More
This CRAH Unit Checklist can be used and completed throughout the project and its different stages covering: Once the pre-functional checks have been completed, including … Read More
A CRAH unit is a critical piece of close control cooling equipment, consisting of filters, fans, coils, that is connected to chilled water/cooling water pipework … Read More
This CRAC Unit Checklist can be used and completed throughout the project and its different stages covering: Once the pre-functional checks have been completed, including … Read More
A CRAC unit is a critical piece of cooling equipment, consisting of filters, fans, coils, and an external direct expansion [dx] condenser, that is connected … Read More
Once the flushing and cleaning activities have been completed, including the backflushing, there will usually be a delay until the handover as other commissioning works … Read More
Made of similar metals and materials to the system components; scaling and or corrosion coupons are installed within a hydraulic system [chilled water/condenser water] to … Read More
This flushing & cleaning pre-works checklist can be used and completed throughout the project and its different stages covering: Once the pre-functional checks have been … Read More
After the system flushing steps have been completed covering the Dynamic Flush, Chemical Flush, Clean Flush, and Passivation/Inhibition, the coil flushing, previously known as ‘back … Read More
Within the pipework cleaning and flushing process, the chemical cleaning stage will be started after the dynamic flushing has been completed successfully, with the water … Read More
The dynamic flushing stage is completed to remove the majority of the debris, dirt, and particles from inside the pipework system prior to moving on … Read More
Just installing new pipework for a closed-loop hydraulic system within a facility that is used for transporting heating/cooling water will not guarantee its internal cleanliness, … Read More
This General Pipework checklist can be used and completed throughout the project and its different stages covering: Once the pre-functional checks have been completed, including … Read More