This CRAC Unit Checklist can be used and completed throughout the project and its different stages covering:
delivery,
storage,
installation &
pre-commissioning/pre-functional
Once the pre-functional checks have been completed, including all equipment and ancillaries related to the system, the full functional testing/commissioning can be conducted.
To know more on CRAC Units, including what they are, types, components etc, see our article 'CRAC UNITS | What are they?'
Once the CRAC Unit & Condenser arrives at the site, usually delivered by a transport company, and before being accepted into storage, the following should be checked with the driver.
Any damage that is noted should be reported to the manufacturer/supplier immediately days in writing supported with photographs.
Ref
Inspection/Task
1
Supplier's consolidated delivery ticket is available, showing all equipment and ancillaries for inspection and being used to check against.
2
A copy of the order that was sent to the supplier is available for reference and is being used to check against.
3
Equipment is packaged and crated in separate boxes, for maximum protection.
4
The unit nameplates and details match the purchase order.
5
Delivery protection is dry.
6
Unit/s are dry internally.
7
The external casing of the unit/s is undamaged.
8
All frames, if ordered are included.
9
All pipework connections are the correct size.
10
Pipework connections are undamaged.
11
All pipework handings are correct.
12
All ventilation opening connections [supply & extract] are correct size.
13
All ancillaries [valves, actuators, dampers, filters] are included in delivery as per the order and delivery note.
14
Spin the fan/s to ensure not damaged and out of line.
15
Check all coils for damage externally and internally.
16
Replace and protection that has been removed.
Storage Inspection
Storage Area
If the equipment is to be placed into storage on site prior to installation there will be an inspection completed checking the following.
Ref
Inspection/Task
1
The area is internal and will not be affected by the weather. [if the unit is not rated for external use]
2
The surface where the equipment is to be placed is flat.
3
The equipment will be raised from the floor to allow airflow and stop the risk of water ingress.
4
The area is well covered and protected.
5
The area is well ventilated and has no risk of high humidity.
Please do not underestimate the impact your purchase can have on this site; it allows us to re-invest in more content/resources, keeping those annoying banner adverts away.
Storage of CRAC Unit & Condenser
Prior to the units being placed into storage, the following should be checked.
Ref
Inspection/Task
1
Units will not be stacked.
2
Units will not have materials stacked on them.
3
All ancillaries will be placed in a safe and secure location, so items do not go missing or get damaged.
4
All original packaging is intact and not removed.
5
Pipework caps are not removed.
6
Unit and all components placed on a flat surface.
Pre-Installation Inspection
Prior to the units being installed the following should be checked.
Ref
Inspection/Task
1
The plinth/base is ready, flat, and level & can bear the weight of the installation.
2
The room/area is dry and watertight.
3
The area being installed is not prone to flooding or ponding of water.
4
The room/area the unit will be installed into is clean and dust-free. If there is dust/construction work, then the unit should be protected.
5
The condenser unit, if installed externally, ensures it can be fixed to the slab and in line with the manufacturers instructions /requirements.
6
If there is a buildup of snow it will not affect the condenser units operation of maintenance requirements.
7
The installation of the CRAC Unit will not impede the installation of the condensate trap/pipework.
8
If any plenums are being installed on the CRAC Unit, there is enough space and there will be no impact on other services.
9
The air openings, supply, and return will not be blocked by any services, and the free area of the opening, as required by the manufacturer, is achievable.
10
All connections, pipework/ductwork [where installed], can be independently supported and not supported by the units. The best practice is to install self-supporting brackets prior to the connection of the unit.
11
Ensure that all access doors are clear and not blocked from brackets or other services.
12
Check to ensure that all connection kits containing - gaskets, bolts, cleats, screws are available to allow bolting up of the equipment.
13
Remove all transport feet and bolts.
14
Check that all required cabling can be run through the unit and on appropriate containment.
Maintenance/Access
Ref
Inspection/Task
1
There is enough space allowed around and above the CRAC Unit once installed to perform maintenance and remove components. [check the manufacturer's maintenance instructions for requirements]
2
There is enough space allowed around and above the Condenser Unit once installed to perform maintenance and remove components. [check the manufacturer's maintenance instructions for requirements]
3
All doors can be fully opened to gain access to the unit.
4
Check that there is enough space for filters, coils, and fans to be removed and replaced.
5
Confirm that there is a safe manner to remove the parts and components of the units and that there is enough space at the high level and at the floor level to allow this.
The refrigerant coil is clean, in good condition, and the fins undamaged.
2
External condenser installed.
3
Ensure that the gas and suction pipework connections are the correct size.
4
Ensure that the gas and suction pipework handing’s are correct.
5
The installation of the pipework will not put stress on the equipment connections or create vibrations.
6
The materials used between the equipment and the refrigeration pipework system will not cause Electrolysis.
7
Pipework that is to connect to the unit has been pressure/vacuum tested.
8
The system is charged with the correct type and amount of refrigerant.
9
Pipework is insulated and vapor sealed.
10
Insulation is labeled.
11
All solenoids installed and operating.
12
All sight glasses installed.
13
All valves/control/expansion valves are installed and in the correct direction.
Electric Reheat Coil
Ref
Inspection/Task
1
Operation of the reheat coil is fan controlled/interlocked
2
Fan delay incorporated into the controls logic, allowing the fan to run [15 mins] after the heater has deactivated/switched off.
3
Heater elements are clean and not obstructed by debris
4
All electrical testing has been completed including torque tests of connections.
5
All safety components are connected and operational including all thermostats to cut power to the heater if needed.
6
All controls cabling is connected and installed in line with the manufacturers/design drawings.
7
Power is available to the electric heater/control panel for operation.
Humidifier
Ref
Inspection/Task
1
Unit is electrically connected with testing completed to electrical components.
2
Humidifier internals is clean and clear of debris.
3
Condensate pipework is installed [see condensate section].
4
Coldwater feed is connected to the humidifier unit.
5
Connections between the standalone unit and the humidifier are using the specific manufacturer's hoses
6
The hoses and pipework that are connected are installed in line with the manufacturers requirements. No tight bends, or kinks.
7
Metal clamps are used to connect the pipework between the humidifier and the standalone unit.
8
Controls valves fitted and operating to allow cold water into the system.
9
Check that the humidity sensor is calibrated.
Cold Water Feed
Ref
Inspection/Task
1
Pipework pressure tested
2
Pipework insulated and vapor sealed
3
Insulation is labeled.
4
All valves fitted and operating [isolation, non-return]
Condensate Pump / Condensate Pipework
Ref
Inspection/Task
1
The condensate pump has been installed in line with the manufacturer's requirements.
2
Condensate pipework connected.
3
The condensate is installed to the correct fall.
4
The size of the condensate is correct.
5
If there are multiple coils installed on a unit, ensure the condensate pipework configuration is installed in line with the manufacturers requirements.
6
Ensure the drain pan is clean and free of debris.
7
Condensate pipework has been flowed tested.
8
Pressurized part of the condensate pipework pressure tested.
9
Pipework flow tested.
10
Pipework insulated and vapor sealed, where required.
11
Insulation is labeled.
12
The pump is electrically connected with testing completed to electrical components.
13
Controls are connected and available.
14
Pump tested and operated in line with project requirements.
Supply Air Ductwork
Ref
Inspection/Task
1
Where required, all supply air ductwork is installed, correct size, and connected to the unit with correct fixings
2
Ductwork insulated and vapor seal in line with the specification.
3
Test holes available in the duct to allow air readings
Hot / Cold Aisle Containment
Ref
Inspection/Task
1
Where installed, Cold Aisle containment has been completed, including all doors and there are no air gaps with ceiling or panels.
2
Where installed, Hot Aisle containment has been completed, including all doors and there are no air gaps with ceiling or panels.
3
All ceilings are completed and there are no gaps.
CONDENSER UNIT Pre-Commissioning Inspection
General
Ref
Inspection/Task
1
Document the information of each unit from its nameplate and cross-reference with the specified information to ensure correct.
2
Ensure each unit is level.
3
Check that all transport bolts and feet are removed.
4
All vibration mounts installed.
5
Seismic restraints, where required, installed.
6
Unit and all components including valves and controls are installed and labeled in line with the project naming convention.
7
Operation and startup manual for the Condenser available.
Electrical General
Ref
Inspection/Task
1
Units and their components are fully earthed in line with the manufacturers instructions.
2
Earthing has been tested
3
Emergency disconnect installed for each component in line with NFPA/local code requirements.
4
Electrical voltage from the site matches the unit required voltages.
5
All cabling is installed and connected on the correct containment/raceways and not damaged.
6
All cabling has been tested/torque tested.
7
A local motor control panel [LMCP] has been installed.
8
The local motor control panel has been electrically tested.
9
All electrical cabling is labeled in line with the project naming convention.
Variable Speed Drive
Ref
Inspection/Task
1
A variable speed drive has been installed.
2
Variable Speed Drive [VSD] has been electrically tested.
3
Variable speed drive has been functionally tested.
Condenser Fans
Ref
Inspection/Task
1
Electrical connections and cables are complete, fully tested, and torqued in line with project/manufacturer requirements.
2
Motor protection installed and operating [Overload].
3
Motor protections calibrated.
4
Voltage from electrical systems is correct for the unit requirements.
5
The fan housing is clean and dust-free.
6
Fan, blades, and motors are clean and dust-free.
7
Ensure the fan is true and aligned correctly.
8
Check the tightness of fixings [torque].
9
Fan/motor rotates in the correct direction with no obstructions [by hand].
10
Fan/motor rotates in the correct direction with no obstructions [electrically bump unit on].
Condenser Coil
Ref
Inspection/Task
1
The refrigerant coil is clean, in good condition, and the fins undamaged.
2
Ensure that the gas and suction pipework is connected and the correct size.
3
Ensure that the gas and suction pipework handings are correct.
4
The installation of the pipework will not put stress on the equipment connections or create vibrations.
5
The materials used between the equipment and the refrigeration pipework system will not cause Electrolysis.
6
Pipework that is to connect to the unit has been pressure/vacuum tested.
7
The system is charged with the correct type and amount of refrigerant.
8
Pipework is insulated and vapor sealed.
9
Insulation is labeled.
10
All solenoids installed and operating.
11
All sight glasses installed.
12
All valves/control/expansion valves are installed and in the correct direction.
We have formatted the above into an Open copy of [Microsoft Word] + [Microsoft Excel] for purchase at a nominal cost to help grow the site and resources. If you would like an open copy emailed to you, click the button to be taken to our shop.
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional
Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes.The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
We use cookies to enhance your browsing experience and analyze website traffic. By clicking “Accept,” you agree to our use of cookies. You can manage your preferences or withdraw consent at any time. For more information, please review our Privacy Policy.
Functional
Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes.The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.