This General Pipework checklist can be used and completed throughout the project and its different stages covering:
- delivery,
- storage,
- installation &
- pre-commissioning/pre-functional
Once the pre-functional checks have been completed, including all equipment and ancillaries related to the pipework system, the full functional testing/commissioning can be conducted.
This checklist should be used and completed throughout the project, and its different stages, delivery, storage, installation & pre-commissioning, before the functional testing occurs.
Delivery Inspection
Once the Pipework arrives at the site, usually delivered by a transport company, and before being accepted into storage, the following should be checked with the driver.
Any damage that is noted should be reported to the manufacturer/supplier immediately in writing supported with photographs.
Ref | Inspection/Task |
---|---|
1 | Supplier's consolidated delivery ticket is available, showing all equipment and ancillaries for inspection and being used to check against. |
2 | A copy of the order that was sent to the supplier is available for reference and is being used to check against. |
3 | Pipework is packaged with end caps to protect the internal surfaces. |
4 | Pipework has the correct wall thickness. |
5 | Pipework has the correct flanges. |
6 | Pipework is dry internally. |
7 | Pipework is not damaged. |
8 | Pipework surfaces are clean and not scratched |
9 | Red oxide paint has been applied, where required and is in good condition. |
10 | All ancillaries are included in delivery as per the order and delivery note |
11 | Replace any protection that has been removed |
Storage Inspection
Storage Area
If the pipework is to be placed into storage on site prior to installation there will be an inspection completed checking the following.
Ref | Inspection/Task |
---|---|
1 | The area is internal and will not be affected by weather. |
2 | If the pipework is not to be stored internally but externally, there is sufficient protection available to protect it from weather and ambient conditions. |
3 | The surface where the pipework is to be placed is flat. |
4 | The area is well covered and protected. |
5 | The area is well ventilated and no risk of high humidity. |
6 | The area is clean & dust free. |
Here is our open copy [MS Word] of the GENERAL PIPEWORK Pre-Functional Checklist, for making life a little easier...
We have also recently formatted this checklist to [MS Excel] and included it as a Bonus for FREE.
So get an MS Word & MS Excel for the same price.
Storage of the Pipework
Prior to the pipework being placed into storage, the following should be checked.
Ref | Inspection/Task |
---|---|
1 | Pipework will not be over stacked. |
2 | Pipework will not have materials stacked on it. |
3 | All ancillaries will be placed in a safe and secure location, so items do not go missing or get damaged. |
4 | Pipework/connection caps protecting the flanges are not removed. |
5 | The pipework will be raised from the floor to allow airflow and stop risk of water ingress. |
We have created this bundle to consolidate all the Equipment Pre-Commissioning and Maintenance Checklists that are available across the site.
The checklists are provided in Microsoft Word and Excel.
Pre-Installation Inspection
Prior to the pipework being installed the following should be checked.
Ref | Inspection/Task |
---|---|
1 | The bracketry is ready and can bear the weight of the installation and has been spaced correctly. |
2 | The room/area is dry and watertight. |
3 | Area being installed is not prone to flooding or ponding of water. |
4 | The room/area the pipework will be installed into is clean and dust-free. If there is dust/construction work, then the pipework should be protected from concrete dust, cement etc. |
5 | Check to ensure that all connection kits containing - gaskets, bolts, are available to allow bolting up of the pipework. |
6 | Pipework is clean and free of damage |
Maintenance/Access
Ref | Inspection/Task |
---|---|
1 | There is enough space allowed around and above the pipework once installed to perform maintenance and remove components, where required. [check the manufacturer's maintenance instructions for requirements] |
Pre-Commissioning Inspection
Once the pipework has been installed and prior to the functional testing and commissioning phase taking place, the following will be checked.
General
Ref | Inspection/Task |
---|---|
1 | Pipework is installed in line with the project drawings [size, location]. |
2 | Piping is free to expand and contract without noise or damage to hangers, joints, or the building. |
3 | Seismic restraints, where required, installed. |
4 | Pipework does not put undue stress on equipment, where connected and is bracketed to support itself. |
5 | All piping supports and hangers meet criteria set out in the specifications. |
6 | Piping is installed with sufficient pitch and arranged in a manner to ensure drainage and venting of the entire system. |
7 | Manual air vents are provided at high points in closed water systems. |
8 | Ensure all gaskets are installed and sealed. |
9 | Ensure that all bolts are installed as per manufacturer's instructions. |
10 | Any nipples installed are made of the same material as the pipe. |
11 | Any connections between copper and steel pipes are made with dielectric fittings. |
12 | A union is provided ahead of each screwed valve, trap, or strainer, and on each side of each piece of equipment and whatever needed to dismantle piping. |
13 | Any changes in pipe sizes are made with the proper size reducing fittings, reducing fittings, reducing elbow, or reducing tees. Bushings are not allowed. |
14 | All fittings meet specification requirements. |
15 | All fittings and ancillaries are rated correctly and inline with the pressure of the system. |
16 | All equipment requiring maintenance is accessible (valves, junction boxes, etc.). |
17 | Piping does not block access to equipment that is part of this system or another system (e.g., air terminal units). |
18 | Drain valves are provided at all low points in hose bib piping to facilitate seasonal draining. |
19 | All valves [isolation, commissioning, non-return etc] are installed as per the drawings |
20 | All strainers are installed as per the drawings and baskets are clean. |
21 | Pipework is insulated as per the specification and vapor sealed where required. |
22 | Piping is installed in a manner to ensure that insulation will not contact adjacent surfaces. |
23 | Any pipe openings are temporarily sealed to maintain piping system cleanliness. |
24 | All components including valves and controls are labeled in line with the project naming convention. |
25 | Instruments, flow meters, energy meters, and commissioning stations have been installed in line with the manufacturer's requirements and correct direction. This includes distances from turbulent flows etc. |
26 | All pressure gauges installed, and display scale as per design requirements. |
27 | Pipework has been magnetic weld tested, where specified. |
28 | Pipework has been ultrasonic weld tested, where specified. |
29 | System has been filled and bled with air removed. |
30 | Pipework has been pressure tested. |
31 | Pipework has been internally flushed, cleaned and chemically treated. |
Documentation
Ref | Inspection/Task |
---|---|
1 | All drawings have been updated to reflect any changes made. |
General Pipework Checklist [Open]
To help us expand the site and create more resources, we have created the below documentation in [Microsoft Word] for download.
Click the ‘Buy Here‘ button to purchase the fully editable copy of the document below, which can be used straight away.
You will direct to our shop page.