Level 6 – Closeout & Turnover

Level 6 is the seventh stage of the data center / critical system commissioning process covering the closeout & turnover of the project.

It would usually be led by the client CxA [commissioning provider/authority]

This level is completed to ensure that the client and end-user agree that the project documentation has been completed and that there are no outstanding works.

This stage will cover:

- Ensuring all L5 reports have been approved,

- Closing out and resolving all defects and punch lists,

- Issuing of final operating and maintenance manuals,

- Issuing of building log books/systems manual,

- Complete lessons learned workshop, document, and create/issue schedule to the client team,

- Finalize owners project requirement document [OPR] and basis of design document [BOD],

- Complete final settings verification on all critical equipment,

- Complete training of building operator/facility engineers,

- Complete and issue final commissioning report,

- Complete and issue closeout/turnover report,

- Client acceptance that the systems and data center have been proved to be operating as per the project requirements and design.

This is then followed by Level 7
« Back to Building Commissioning Glossary Index