This pump commissioning checklist can be used and completed throughout the project and its different stages:
- delivery,
- storage,
- installation &
- pre-commissioning
Once completed, the full functional testing of the pumps can be conducted.
To read our article on Pump Testing see 'Pump Commissioning and Alignment'
Delivery Inspection
Once the Pump arrives at the site, usually delivered by a transport company, and before being accepted into storage, the following should be checked with the driver.
Any damage that is noted should be reported to the manufacturer/supplier within 3 days in writing, supported with photographs.
Ref | Inspection/Task |
---|---|
1 | Supplier's consolidated delivery ticket is available, showing all equipment and ancillaries for inspection and being used to check against. |
2 | A copy of the order that was sent to the supplier is available for reference and is being used to check against |
3 | Equipment is packaged and crated in separate boxes for maximum protection. |
4 | The pump & pump motor nameplate and details match the purchase order. |
5 | Delivery protection is dry. |
6 | Pump/s are dry internally. |
7 | The external casing of the pump/s is undamaged. |
8 | All base frames, if ordered are included. |
9 | All pipework connections are the correct size. |
10 | Flanges and Pipework connections are undamaged. |
11 | All ancillaries are included in delivery as per the order and delivery note. |
12 | Spin the pump impeller to ensure it is not damaged and out of line |
13 | Replace and protection that has been removed |
Storage Inspection
Storage Area
If the pumps are to be placed into storage on-site before installation, there will be an inspection completed checking the following.
Ref | Inspection/Task |
---|---|
1 | The area is internal and will not be affected by the weather. [if the pump is not rated for external use] |
2 | The surface where the equipment is to be placed is flat. |
3 | The area is well covered and protected. |
4 | The area is well ventilated and has no risk of high humidity. |
5 | The area is clean & dust-free. |
Here is our open copy [MS Word] of the CENTRIFUGAL PUMP Pre-Functional Checklist, for making life a little easier...
We have also recently formatted this checklist to [MS Excel] and included it as a Bonus for FREE.
So get an MS Word & MS Excel for the same price.
Storage of the Pump
Prior to the pump/s being placed into storage, the following should be checked.
Ref | Inspection/Task |
---|---|
1 | Pumps will not be stacked. |
2 | Pumps will not have materials stacked on them. |
3 | All ancillaries will be placed in a safe and secure location, so items do not go missing or get damaged. |
4 | All original packaging is intact and not removed. |
5 | Pipework/connection caps protecting the flanges are not removed. |
6 | The pumps will be raised from the floor to allow airflow and stop the risk of water ingress. |
Pre-Installation Inspection
Prior to the pumps being installed, the following should be checked.
Ref | Inspection/Task |
---|---|
1 | The plinth/base is ready, flat, and level & can bear the weight of the installation. |
2 | The room/area is dry and watertight. |
3 | The area being installed is not prone to flooding or ponding of water. |
4 | The room/area the pumps will be installed into is clean and dust-free. If there is dust/construction work, then the pumps should be protected. |
5 | If the pumps are installed externally, if there is a buildup of snow, it will not affect the pump/s operation or maintenance requirements. |
6 | All pipework connections can be independently supported and not supported by the pump/s. The best practice is to install self-supporting brackets prior to the connection. |
7 | Check to ensure that all connection kits containing gaskets and bolts are available to allow bolting up the pumps to the system. |
8 | Remove all transport feet and bolts. |
Maintenance/Access
Ref | Inspection/Task |
---|---|
1 | There is enough space allowed around and above the pumps once installed to perform maintenance and remove components. [check the manufacturer's maintenance instructions for requirements] |
Pre-Commissioning Inspection
Once the pumps have been installed and before the functional testing and commissioning phase occur, the following will be checked.
General
Ref | Inspection/Task |
---|---|
1 | Document the information of the pump from its nameplates and cross-reference with the specified information to ensure correct. |
2 | Check that all transport bolts and feet are removed. |
3 | Ensure pump/s are level. |
4 | Ensure all gaskets are installed and sealed. |
5 | Ensure that all bolts are installed as per the manufacturers instructions. |
6 | Ensure pumps are aligned in accordance with the manufacturers instructions. |
7 | All vibration mounts installed. |
8 | Seismic restraints, where required, installed. |
9 | All components, including valves and controls, are labeled in line with the project naming convention. |
10 | Operation and startup manual for the Pumps available. |
Electrical General
Ref | Inspection/Task |
---|---|
1 | Pump/s and components are fully earthed in line with the manufacturers instructions. |
2 | Earthing has been tested. |
3 | Emergency disconnect installed for each pump in line with NFPA/local code requirements. |
4 | Electrical voltage from the site matches the pump required voltages. |
5 | All cabling is installed and connected on the correct containment and not damaged. |
6 | All cabling has been tested/torque tested. |
7 | A local motor control panel [LMCP] has been installed. |
8 | The local motor control panel has been electrically tested. |
9 | All electrical cabling is labeled in line with the project naming convention. |
Variable Speed Drive
Ref | Inspection/Task |
---|---|
1 | A variable speed drive has been installed. |
2 | Variable Speed Drive [VSD] has been electrically tested |
3 | Variable speed drive has been functionally tested. |
We have created this bundle to consolidate all the Equipment Pre-Commissioning and Maintenance Checklists that are available across the site.
The checklists are provided in Microsoft Word and Excel.
Controls System Interlocks
Ref | Inspection/Task |
---|---|
1 | Controls system installed as per the drawings and control logics and interlocked with other cooling/heating plant. |
Pumps/Pipework
Ref | Inspection/Task |
---|---|
1 | Ensure that the pump is installed in the correct orientation to the system pipework and the impeller rotates in the correct direction. |
2 | Ensure that the pipework and connections are the correct size and in line with the drawing. |
3 | Check that the pipework installation is in line with the manufacturers information. There is usually a requirement of the straight length, connecting to the inlet side of the pump, be at least 10x the pipework diameter. |
4 | Ensure the installation of the pipework will not put stress on the Pump connections or create vibrations. |
5 | The materials used between the pump/s and the chilled water system will not cause Electrolysis. |
6 | Pipework that is to connect to the pump/s has been weld tested. |
7 | Pipework that is connected to the pump/s has been pressure tested. |
8 | Pumps have been primed in line with the manufacturers requirements. |
9 | Pipework that is connected to the pump/s has been cleaned and flushed. |
10 | The system has been bled and the air removed. |
11 | Pipework is insulated and vapor sealed. |
12 | Insulation is labeled |
13 | All pressure gauges installed and display scale as per design requirements. |
14 | All valves/control valves are installed and in the correct direction. |
15 | All commissioning devices are installed. |
16 | All Strainers are installed and inspected to ensure the mesh is clean. |
17 | All expansion/rubber bellows are installed at least 1.5x the pipe diameter away from the pump for the inlet and the outlet. |
Controls
Ref | Inspection/Task |
---|---|
1 | Ensure all sensors and instruments are installed as per the control logic/pipework schematic drawings [pressure sensors, flow sensors, etc.] |
2 | All sensors are calibrated. |
Centrifugal Pump Commissioning Checklist [PDF]
To help us expand the site and create more resources, we have created the below documentation in [Microsoft Word] + [Microsoft Excel] for download.
Click the ‘Buy It Now‘ button to purchase the fully editable copy of the document below, which can be used straight away.
You will direct to our shop page.