Skip to content
constructandcommission.com
    constructandcommission.com
    • DOC SHOP
      • Bundles [SAVINGS]
      • Cx Process [ALL]
      • Checklists [ALL]
      • Data Center [ALL]
      • Testing Procedures [ALL]
      • Fire [ALL]
      • Mechanical [ALL]
      • Maintenance [ALL]
    • CX PROCESS
      • COMMISSIONING PLAN
      • Cx Kick Off Meeting
      • Basis of Design
      • Overview of the Cx Process
      • Stage 1: Pre-Design
      • Stage 2: Design
      • Stage 3a: Pre-Construction explained
      • Stage 3b: Construction
      • Stage 3c: Commissioning
      • Stage 4: Occupancy and Operations
      • Stage 5: Continuous Commissioning
    • FIRE
      • Sprinkler Systems
      • Suppression Systems
      • FM-200
    • MECHANICAL
      • Chilled Water
      • Condenser Water
      • Heating Water
      • Ventilation
    • OTHER
      • PRE-FUNCTIONAL CHECK LISTS
      • DATA CENTER
      • LEED
      • ELECTRICAL
      • PLUMBING & DRAINAGE
      • HANDOVER
      • MAINTENANCE
    • Glossary
    constructandcommission.com
    • DOC SHOP
      • Bundles [SAVINGS]
      • Cx Process [ALL]
      • Checklists [ALL]
      • Data Center [ALL]
      • Testing Procedures [ALL]
      • Fire [ALL]
      • Mechanical [ALL]
      • Maintenance [ALL]
    • CX PROCESS
      • COMMISSIONING PLAN
      • Cx Kick Off Meeting
      • Basis of Design
      • Overview of the Cx Process
      • Stage 1: Pre-Design
      • Stage 2: Design
      • Stage 3a: Pre-Construction explained
      • Stage 3b: Construction
      • Stage 3c: Commissioning
      • Stage 4: Occupancy and Operations
      • Stage 5: Continuous Commissioning
    • FIRE
      • Sprinkler Systems
      • Suppression Systems
      • FM-200
    • MECHANICAL
      • Chilled Water
      • Condenser Water
      • Heating Water
      • Ventilation
    • OTHER
      • PRE-FUNCTIONAL CHECK LISTS
      • DATA CENTER
      • LEED
      • ELECTRICAL
      • PLUMBING & DRAINAGE
      • HANDOVER
      • MAINTENANCE
    • Glossary
    Level 6 Data Center Commissioning Step by Step Guide

    LEVEL 6 – DATA CENTER COMMISSIONING | Closeout & Turnover

    Level 6 of the Data Center Commissioning Process moves the project from the onsite commissioning phase to close out, turn over, and hand over. The … Read More

    Level 5 Data Center Integrated Commissioning Step by Step

    LEVEL 5 – DATA CENTER COMMISSIONING | Integrated Testing

    The Level 5 Integrated Testing for a Data Center aims to validate that all installed mechanical, electrical, fire, BMS, and controls systems, including equipment, operate … Read More

    Level 4 Data Center Functional Commissioning Step by Step

    LEVEL 4 – DATA CENTER COMMISSIONING | Functional Testing

    The Level 4 Data Center Commissioning Stage is usually where the General/Main Contractor hands over the testing responsibilities to the Client Commissioning Agent. The Commissioning … Read More

    Level 3 Data Center Start-Up Commissioning Steps

    LEVEL 3 – DATA CENTER COMMISSIONING | Pre-Functional/Start-Up

    For Data Center Commissioning, the Level 3 Stage focuses on the following tasks and activities as listed below, proving that the systems have been installed, … Read More

    Level 2 Data Center Component Delivery Commissioning Step by Step

    LEVEL 2 – DATA CENTER COMMISSIONING | Component Delivery

    Level 2 is the third stage/process to be completed after Level 1. Its focus is on verifying components, equipment, and materials after they have been … Read More

    Level 1 Data Center Factory Commissioning Step by Step

    LEVEL 1 – DATA CENTER COMMISSIONING | Factory Testing

    Within Data Center Commissioning, Level 1 is the second stage to be completed after Level 0. Its focus is on the Factory Testing Requirements and … Read More

    Level 0 Data Center Design & Planning Commissioning Step by Step

    LEVEL 0 – DATA CENTER COMMISSIONING | Design & Planning

    Within Data Center Commissioning, Level 0 is usually the first stage to be started, it focuses upon the design and planning of the projects data … Read More

    LEED Enhanced vs Fundamental Commissioning

    LEED Fundamental vs Enhanced Commissioning

    If you have ever wondered what the difference is between the LEED FUNDAMENTAL & ENHANCED Commissioning process, here is a table that lists out the … Read More

    LEED Enhanced Commissioning Article

    Described + Tasks | LEED ENHANCED COMMISSIONING

    LEED Enhanced Commissioning is a process completed under the U.S Green Building Council Pre-Requisite V4 BD+C New Construction, with its aim being the same as … Read More

    LEED Fundamental Commissioning Tasks

    Described + Tasks | LEED FUNDAMENTAL COMMISSIONING

    LEED Fundamental Commissioning is a process completed under the U.S Green Building Council Pre-Requisite 1 EA Module, with its aim being that all fundamental systems … Read More

    As-built Drawings

    AS-BUILT DRAWINGS | What are they?

    Produced in the latter stages of the project by the construction project team, as-built drawings provide the final design and installation information of a project … Read More

    CRAC Unit Functional Testing Front

    CRAC UNIT | Functional Testing Example + Template

    Upon completion of any new CRAC [computer room air conditioning] Unit installation or modifications to an existing unit, there will be a requirement to complete … Read More

    Lookahead Schedule Front

    LOOK AHEAD SCHEDULES | 2,3&4 weeks + FREE templates

    Read in conjunction with the overall project programme, look ahead schedules are used within the latter stages of the construction and commissioning phases of a … Read More

    Group Control Overview for CRAH/CRAC Units

    GROUP CONTROL | CRAH & CRAC Units

    Whether deploying a Hot Standby or Cold Standby strategy to condition a critical space, ‘Group Control’ will be used where multiple CRAH or CRAC Units … Read More

    CRAH Unit Functional Testing Procedure

    CRAH UNIT | Functional Testing Example + Template

    Upon completion of any new CRAH [computer room air handling] Unit installation or modifications to an existing unit, there will be a requirement to complete … Read More

    Gas Suppression Functional Testing Method

    GASEOUS/FM200 SYSTEM | Functional Testing Template & Download

    Upon completion of any new Gaseous / Clean Agent System installation or modifications to an existing system, there will be a requirement to complete a … Read More

    FM200 System Pre-Functional Checklist

    GAS SUPPRESSION / FM 200 SYSTEM | Pre-Functional Checklist

    This FM 200 / Gas Suppression Pre-Functional Test Checklist can be used and completed throughout the project and its different stages covering: delivery, storage, installation … Read More

    [090] How does a FM200 System Work

    FM200 SYSTEM | How does it Work?

    The most common type of FM200 System seen is a total flooding, automatically operated one using zoned smoke heads, installed at a high level and … Read More

    [091] Building Log Book with PDF

    BUILDING LOG BOOK | What and Why?

    Under the Building Regulations [England], Approved Document L2A, a Building Log Book should be written and issued to the building owner/operator no later than five … Read More

    [084] Room-Integrity-Requirements-Front

    CLEAN AGENT | Room Integrity Testing Requirements

    When installing a fixed firefighting gas extinguishing system, under NFPA 2001 and BS EN 15004-1, there is a requirement to complete a Room Integrity/Enclosure Test. … Read More

    Older posts
    Newer posts
    ← Previous Page1 Page2 Page3 … Page7 Next →

    We are a participant in the Amazon Services LLC Associates Program, an affiliate advertising program designed to provide a means for us to earn commissions by linking to Amazon.com and affiliated sites.

    ABOUT US | PRIVACY POLICY | WEBSITE DISCLAIMER | © 2021 constructandcommission.com

    Next Page »
    • DOC SHOP
      • Bundles [SAVINGS]
      • Cx Process [ALL]
      • Checklists [ALL]
      • Data Center [ALL]
      • Testing Procedures [ALL]
      • Fire [ALL]
      • Mechanical [ALL]
      • Maintenance [ALL]
    • CX PROCESS
      • COMMISSIONING PLAN
      • Cx Kick Off Meeting
      • Basis of Design
      • Overview of the Cx Process
      • Stage 1: Pre-Design
      • Stage 2: Design
      • Stage 3a: Pre-Construction explained
      • Stage 3b: Construction
      • Stage 3c: Commissioning
      • Stage 4: Occupancy and Operations
      • Stage 5: Continuous Commissioning
    • FIRE
      • Sprinkler Systems
      • Suppression Systems
      • FM-200
    • MECHANICAL
      • Chilled Water
      • Condenser Water
      • Heating Water
      • Ventilation
    • OTHER
      • PRE-FUNCTIONAL CHECK LISTS
      • DATA CENTER
      • LEED
      • ELECTRICAL
      • PLUMBING & DRAINAGE
      • HANDOVER
      • MAINTENANCE
    • Glossary