Level 2 is the third stage/process to be completed after Level 1. Its focus is on verifying components, equipment, and materials after they have been delivered to the project to ensure that they are in line with the material submission, order, and general project requirements.
If planned correctly, including having the required checklists and documentation in place, the stage is relatively short and uncomplicated to complete focusing on the following:
- Ensuring all delivery checklists are approved and in place,
- Planning and management of the delivery schedule,
- Documenting the receiving of equipment and materials onto site,
- Documenting the onsite pre-installation requirements,
- Provide a Yellow Tag upon completion.
Below, we see more detail about delivering this stage, including explaining the tasks, activities, and responsibilities.
| Step 1 – Write/Issue for Approval Checklists
To ensure that the delivery and acceptance onto the site of the equipment and materials are fully documented and in line with the project requirements, the main/general contractor will write and issue, to the MEP Designer and Commissioning Agent [CxA], the following documents for approval:
- A detailed delivery checklist for each different type of equipment and material,
- Storage area checklist for each type of equipment and material, if not being moved to its site location immediately after delivery.
A reference can be taken from the Level 0 deliverables where the commissioning agent will have provided templates of these documents in the commissioning plan/specification.
Further Reading
We have written the following article for further information on checklists; there are also examples:
Responsibility Matrix
Role | Responsible | Accountable | Consulted | Informed |
---|---|---|---|---|
Client | X | |||
Project Manager | X | |||
Architect | X | |||
Commissioning Provider | X | |||
Green Building Consultant | X | |||
MEP Designer | X | |||
General/Main Contractor | X | |||
Sub Contractor | X | |||
Vendor | X | |||
Building Operations | X |
| Step 2 – Plan and Manage Deliveries
All equipment and materials should be delivered to the project on time and in line with the project programme.
The general/main contractor will manage and coordinate this step to ensure that all deliveries are planned and meet site requirements.
If needed, the main/general contractor could include the dates of this testing within their project 2-week look ahead programme to aid the planning and notification to the project team.
Further Reading
We have written the following article for further information:
Responsibility Matrix
Role | Responsible | Accountable | Consulted | Informed |
---|---|---|---|---|
Client | X | |||
Project Manager | X | |||
Architect | X | |||
Commissioning Provider | X | |||
Green Building Consultant | X | |||
MEP Designer | X | |||
General/Main Contractor | X | |||
Sub Contractor | X | |||
Vendor | X | |||
Building Operations | X |
| Step 3 – Complete Delivery and Storage Checklists
Once a delivery has been received on the site, the general/main contractor should ensure that all paperwork, including the approved checklists, has been completed and any observations noted.
Any observations should be inputted into the ‘Project Issues Register’ for further tracking and closing out if the issues are not critical, where they should be logged and dealt with immediately.
As well as the general/main contractor, the MEP designer or Project QA/QC Team will also participate in these inspections validating the information.
To read more on Issues Registers see our article: 'COMMISSIONING ISSUES LOG | Explained with Template'
Responsibility Matrix
Role | Responsible | Accountable | Consulted | Informed |
---|---|---|---|---|
Client | X | |||
Project Manager | X | |||
Architect | X | |||
Commissioning Provider | X | |||
Green Building Consultant | X | |||
MEP Designer | X | |||
General/Main Contractor | X | |||
Sub Contractor | X | |||
Vendor | X | |||
Building Operations | X |
| Step 4 – Pre-Installation Inspection
Prior to the equipment being installed the main/general contractor will complete a pre-installation inspection and document within the approved project checklists.
The checklists should cover the following:
- Installation pre-requisites,
- Maintenance,
- Builders requirements, and
- General access requirements.
Any observations should be inputted into the ‘Project Issues Register’ for further tracking and closing out if the issues are not critical, where they should be logged and dealt with immediately.
As well as the general/main contractor, the MEP designer or Project QA/QC Team will also participate in these inspections validating the information.
Further Reading
We have written the following article for further information on Checklists; there are also examples:
Responsibility Matrix
Role | Responsible | Accountable | Consulted | Informed |
---|---|---|---|---|
Client | X | |||
Project Manager | X | |||
Architect | X | |||
Commissioning Provider | X | |||
Green Building Consultant | X | |||
MEP Designer | X | |||
General/Main Contractor | X | |||
Sub Contractor | X | |||
Vendor | X | |||
Building Operations | X |
| Step 5 – Manage Documentation and Filing System
Carrying on from the Level 0 & Level 1 commissioning documentation filing system, the general/main contractor should ensure that all documents related to the delivery and storage checklists are filed in line with the project requirements.
Responsibility Matrix
Role | Responsible | Accountable | Consulted | Informed |
---|---|---|---|---|
Client | X | |||
Project Manager | X | |||
Architect | X | |||
Commissioning Provider | X | |||
Green Building Consultant | X | |||
MEP Designer | X | |||
General/Main Contractor | X | |||
Sub Contractor | X | |||
Vendor | X | |||
Building Operations | X |
| Step 6 – Application of Yellow Tag
Once all the above checklists have been completed, the commissioning agent [CxA] will apply the ‘YELLOW TAG’, which will provide visual confirmation that the equipment has completed the Level 2 Data Center Commissioning Process and can move to Level 3.
Responsibility Matrix
Role | Responsible | Accountable | Consulted | Informed |
---|---|---|---|---|
Client | X | |||
Project Manager | X | |||
Architect | X | |||
Commissioning Provider | X | |||
Green Building Consultant | X | |||
MEP Designer | X | |||
General/Main Contractor | X | |||
Sub Contractor | X | |||
Vendor | X | |||
Building Operations | X |
| Step 7 – Update OPR & BOD
Once all checklists have been completed, a review of the Owners Project Requirements Document [OPR] and Basis of Design [BOD] should be conducted by the Commissioning Agent and Designer.
Any changes noted from the Level 2 works; the documents should be updated.
Further Reading
We have written the following articles for further information:
- OWNER’S PROJECT REQUIREMENT | [OPR] What is it & Template
- BASIS OF DESIGN | [BOD] How to Write with download
Responsibility Matrix
Role | Responsible | Accountable | Consulted | Informed |
---|---|---|---|---|
Client | X | |||
Project Manager | X | |||
Architect | X | |||
Commissioning Provider | X | |||
Green Building Consultant | X | |||
MEP Designer | X | |||
General/Main Contractor | X | |||
Sub Contractor | X | |||
Vendor | X | |||
Building Operations | X |
| Step 8 – Issue Level 2 Closeout Certificate
Once all the above has been completed with all issues and observations closed and reinspected, the Data Center Commissioning Level 2 Certificate should be completed and issued to the project before moving on to the Data Center Commissioning Level 3 works.
The main/general contractor should issue this to the commissioning agent [CxA] for review and approval.
Further Reading:
To read more and download a set [Levels 0-7] of Sign-Off Certificates we have written the following:
Responsibility Matrix
Role | Responsible | Accountable | Consulted | Informed |
---|---|---|---|---|
Client | X | |||
Project Manager | X | |||
Architect | X | |||
Commissioning Provider | X | |||
Green Building Consultant | X | |||
MEP Designer | X | |||
General/Main Contractor | X | |||
Sub Contractor | X | |||
Vendor | X | |||
Building Operations | X |
Level 0 to Level 7 Data Center Commissioning Checklist Template [Open / PDF]
To help us expand the site and create more resources, we have created the below documentation in [Microsoft Word] for download.
Click the ‘Buy It Now‘ button to purchase the fully editable copy of the document below, which can be used straight away.
You will direct to our shop page.