If you have ever wondered what the difference is between the LEED FUNDAMENTAL & ENHANCED Commissioning process, here is a table that lists out the tasks and activities that should be completed for both.
As we can see there are a lot of similarities between the two when delivering the basis of a commissioning process.
If you would like to understand more on the LEED Fundamental & LEED Enhanced Commissioning see our articles: 'LEED FUNDAMENTAL COMMISSIONING' and 'LEED ENHANCED COMMISSIONING'
Comparison Table
Task | Fundamental Commissioning | Enhanced Commissioning |
---|---|---|
Develop Owners Project Requirement Document | X | X |
Develop the Basis of Design Document | X | X |
Review and Approve OPR Document | X | X |
Review and Approve BOD Document | X | X |
Complete Design Review | X | X |
Write a Commissioning Plan | X | X |
Incorporate Commissioning Requirements into the Construction Documents | X | X |
Develop the Construction Checklists | X | X |
Review Contractor Submittals | X | |
Develop and Manage all Functional Testing Procedures | X | X |
Verify and Witness System Tests | X | X |
Maintain Issues Register | X | X |
Write and manage Weekly Reports | X | X |
Write and manage Monthly Reports | X | X |
Write and manage Final Reports | X | X |
Create a Systems Manual | X | X |
Verify Operator and Occupant Training Delivery | X | |
Plan and Manage the Delivery of Seasonal Testing | X | |
Develop an Ongoing Commissioning Plan | X | |
Complete 10 month Review | X | |
Enhanced + Monitoring-Based Commissioning - Develop a Monitoring-Based Commissioning Process | X | |
Envelope Commissioning - Review contractor submittals | X | |
Envelope Commissioning - Ensure Included within the System Manual | X | |
Envelope Commissioning - Verify Operator and Occupant Training Delivery | X | |
Envelope Commissioning - Plan and Manage the Delivery of Seasonal Testing | X |