Level 7 – Acceptance

Level 7 is the eighth stage of the data center / critical system commissioning process covering the overall acceptance of the project, documentation, and commissioning results by the client and end-user.

It would usually be led by the client CxA [commissioning provider/authority]

This level is completed to ensure that the client and end-user agree the project has been completed in line with the design and operational expectations with no observations outstanding.

This stage will cover:

- Conduct a Level 7 closeout meeting with the client and end user,

- Agree that all processes and activities have been completed from Levels 1, 2, 3, 4, 5 & 6,

- Agree that all issues and observations have been completed,

- Review of electronic platforms to ensure all commissioning documentation has been uploaded and approved.

- Provide approved final operating and maintenance manuals,

- Provide training records,

- Provide/inspect final cleanliness records of critical spaces,

- Provide final commissioning report,

- Issue and acceptance of Level 7 completion certificate.

This will be the end of the data hall commissioning process.