Level 1 – Factory Testing

Level 1 is the second stage of the data center / critical system commissioning process covering the factory testing stage of the project, to ensure that any specific equipment is tested and undergoes the correct quality assurance process prior to being dispatched from the factory.

This stage will cover:

- Providing documentation, that will be reviewed, such as testing procedures and QA/QC checklists,

- Agreeing on which equipment will be tested,

- Factory testing & QA/QC Checks,

- Reports and data gathering,

- Attachment of the correct tag [Red]

This is then followed by Levels 2, 3, 4, 5, 6 & 7