FM200™ PIPEWORK | Pre-Commissioning Check List

Last Updated: August 13, 2023, by

To monitor the quality of the FM-200 pipework throughout different stages and before testing and commissioning works taking place, checklists will be completed by the project team [client, commissioning manager, designer, and installer/contractor].

The stages at when these checks will be completed are:

  • delivery,
  • storage,
  • installation &
  • pre-commissioning/pre-functional
We have a checklist for the complete Gas Suppression / FM 200 System, see our article 'GAS SUPPRESSION / FM 200 SYSTEM | Pre-Functional Checklist'

Once the delivery, storage, installation, and pre-commissioning/functional checks have been completed, the pressure testing can commence.

🟩 Delivery Inspection

Once the FM-200 pipework and ancillaries arrive at the site, usually delivered by a transport company, the following should be checked with the driver before being accepted into storage.

Any noted damage should be reported immediately in writing to the manufacturer/supplier, supported with photographs.

RefInspection/Task
1Supplier's consolidated delivery ticket is available, showing all equipment and ancillaries for inspection and being used to check the delivery.
2A copy of the order is available for reference and used to review the delivery.
3Pipework is packaged with end caps to protect the internal surfaces.
4Pipework has the correct wall thickness.
5Pipework has suitable flanges.
6Pipework is dry internally.
7Pipework is not damaged.
8Pipework surfaces are clean and not scratched
9Paint has been applied to the pipework where required and is in good condition.
10All ancillaries are included in delivery as per the order and delivery note
11Replace any protection that has been removed
FM-200 Pipework Pressure Testing Pre-Commissioning Checklist [MS Word] + [MS Excel]

Here is our open copy [MS Word] of the FM200 PIPEWORK PRESSURE TESTING Pre-Functional Checklist, for making life a little easier...

We have also recently formatted this checklist to [MS Excel] and included it as a Bonus for FREE. 

So get an MS Word & MS Excel for the same price.

#CC: 085a
Buy Here | $1.99
Please do not underestimate the impact your purchase can have on this site; it allows us to re-invest in more content/resources, keeping those annoying banner adverts away.

🟩 Storage Inspection

🟧 Storage Area

If the FM-200 pipework is to be placed into storage on-site before installation, there should be an inspection completed checking the following.

RefInspection/Task
1The area is internal and shall not be affected by the weather.
2If the pipework & ancillaries are not to be stored internally but externally, there is sufficient protection to protect it from weather and ambient conditions.
3The surface where the pipework & ancillaries are to be placed is flat.
4The area is well covered and protected.
5The area is well ventilated and has no risk of high humidity.
6The area is clean & dust-free.

🟧 Storage of the FM-200 Pipework & Ancillaries

Before the pipework is placed into storage, the following should be checked.

[note: due to the risks involved, the gas cylinders shall not be stored on-site, they shall be delivered and installed just before handover and documented separately].

RefInspection/Task
1Pipework & ancillaries will not be over stacked.
2Pipework & ancillaries shall not have materials stacked on them.
3All ancillaries shall be placed in a safe and secure location so items do not go missing or get damaged.
4Pipework/connection caps protecting the flanges are not removed.
5The pipework shall be raised from the floor to allow airflow and stop the risk of water ingress.

🟩 Pre-Installation Inspection

Before the pipework & ancillaries are installed, the following should be checked.

RefInspection/Task
1The bracketry is ready and can bear the weight of the installation, and has been spaced correctly.
2The room/area is dry and watertight.
3The area being installed is not prone to flooding or ponding of water.
4The room/area the pipework will be installed into is clean and dust-free. If there is dust/construction work, the pipework should be protected from concrete dust, cement.
5Check to ensure that all connection kits containing - gaskets, bolts are available to allow bolting up of the pipework.
6Pipework is clean and free of damage
19No. Site Equipment / Maintenance Checklists [MS Word] [MS Excel]

We have created this bundle to consolidate all the Equipment Pre-Commissioning and Maintenance Checklists that are available across the site.

The checklists are provided in Microsoft Word and Excel.

#CC: [000f]
Buy Now | $8.99

🟩 Maintenance/Access

RefInspection/Task
1There is enough space allowed around and above the pipework once installed to perform maintenance and remove components, where required [check the manufacturer's maintenance instructions for requirements]

🟩 Pre-Commissioning Inspection

Once the pipework has been installed and before the functional testing and commissioning phase, the following shall be checked.

🟧 General

RefInspection/Task
1Pipework & ancillaries are installed according to the project drawings & manufacturers' requirements [size, nozzle location].
2Discharge nozzles are installed and oriented per the manufacturer's requirements.
3Where nozzle deflectors have been installed, they are positioned according to the manufacturer's requirements.
4There is no risk of potential harm or injury from installing the nozzles and bracketry.
5There is no risk of loose objects being stored within the space on shelves, cabinets, or similar surfaces, near to the discharge nozzles from becoming projectiles.
6Piping is free to expand and contract without noise or damage to hangers, joints, or the building.
7Pipework does not put undue stress on ancillaries and equipment, connected and bracketed to support itself.
8Seismic restraints, where required, installed.
9All piping supports and hangers meet criteria set out in the specifications & manufacturers' requirements, including being securely fastened to prevent unwanted vertical or lateral movement during discharge.
10The pipework has been internally inspected to verify that there is no oil or dirt/debris within it that could cause an issue to the operation of the system discharge.
11Any changes in pipe sizes are made with the proper sized reducing fittings.
12All fittings meet specification requirements & manufacturers' requirements.
13All fittings and ancillaries are rated correctly and in line with the system's pressure & manufacturers' requirements.
14All equipment requiring maintenance is accessible (valves, junction boxes).
15Piping does not block access to equipment that is part of this system or another system.
16All valves are installed as per the drawing & manufacturers' requirements.
17Pipework is insulated as per the specification and vapor sealed where required.
18Piping is installed, ensuring that insulation shall not contact adjacent surfaces.
19Any pipe openings are temporarily sealed to maintain piping system cleanliness & integrity for testing.
20All components, including valves and controls, are labeled according to the project naming convention.
21Valves/check valves have been installed according to the manufacturer's requirements and are in the correct direction.
22All pressure gauges installed and display scale as per design & manufacturers' requirements.

🟩 Documentation

RefInspection/Task
1All drawings have been updated to reflect any changes made.

⬜ FM 200 Pre-Functional/Commissioning Pipework Checklist Download [PDF]

To help us expand the site and create more resources, we created the documentation below in [Microsoft Word] for download.

Click the ‘Buy It Here‘ button to purchase the fully editable copy of the document below, which can be used straight away.

You will direct to our shop page.

⬛ Latest Articles


⬛ Author

If you would like to know more about the author, here is my Personal Linkedin Account