This fan coil unit commissioning checklist can be used and completed throughout the project and its different stages covering:
delivery,
storage,
installation &
pre-commissioning
Once the pre-functional checks have been completed, the fan coil unit’s full functional testing/commissioning can be conducted.
This checklist should be used and completed throughout the project, and its different stages, delivery, storage, installation & pre-commissioning, before the functional testing occurs.
Once the Fan Coil Unit arrives at the site, usually delivered by a transport company, the following should be checked with the driver before being accepted into storage.
Any noted damage should be reported to the manufacturer/supplier within 3 days in writing, supported with photographs.
Ref
Inspection/Task
1
Supplier's consolidated delivery ticket is available, showing all equipment and ancillaries for inspection and being used to check.
2
Copy of the order issued to the supplier is available for reference and is being used to check.
3
Equipment is packaged and crated in separate boxes for maximum protection.
4
The unit nameplate and details match the purchase order.
5
Delivery protection is dry.
6
Unit/s are dry internally.
7
The external casing of the unit/s is undamaged.
8
All pipework connections are the correct size.
9
Pipework connections are undamaged.
10
All pipework handings are correct.
11
All ducting connections are the correct size.
12
All ancillaries [valves, actuators, dampers, filters] included in delivery as per the order and delivery note
13
Spin the fan blades to ensure not damaged and out of line
14
Check all coils for damage externally and internally.
15
Check drip pan/condensate pan for damage, including insulation.
16
If purchased, check plenums for damage and ensure they are the correct sizes & spigots.
17
Replace any protection that has been removed
Storage Inspection
Storage Area
If the equipment is to be placed into storage on-site before installation, there will be an inspection completed checking the following.
Ref
Inspection/Task
1
The area is internal and will not be affected by the weather. [if the unit is not rated for external use]
2
The surface where the equipment is to be placed is flat.
3
The equipment will be raised from the floor to allow airflow and stop the risk of water ingress.
4
The area is well covered and protected.
5
The area is well ventilated and has no risk of high humidity.
Please do not underestimate the impact your purchase can have on this site; it allows us to re-invest in more content/resources, keeping those annoying banner adverts away.
Storage of Fan Coil Unit
Before the units being placed into storage, the following should be checked.
Ref
Inspection/Task
1
Units will not be stacked.
2
Units will not have materials stacked on them.
3
All ancillaries will be placed in a safe and secure location, so items do not go missing or get damaged.
4
All original packaging is intact and not removed.
5
Pipework caps are not removed.
6
Ductwork connections are covered to stop the ingress of dirt and foreign objects.
7
Unit and all components placed on a flat surface.
Pre-Installation Inspection
Prior to the units being installed, the following should be checked.
Ref
Inspection/Task
1
The slab/wall/base is ready, flat, and level & can bear the weight of the installation and bracketry.
2
If being installed above an existing ceiling, ensure that there is enough space through the ceiling grid to install the unit and ancillaries.
3
The room/area is dry and watertight.
4
The area being installed is not prone to flooding or ponding of water. [for wall mounted/floor mounted units]
5
The room/area the unit will be installed into is clean and dust-free. If there is dust/construction work, then the unit should be protected.
6
If the unit has a ventilation supply, ensure it is installed ready for connecting, or the louver has been installed, if direct fresh air.
7
The installation of the unit will not impede the installation of the condensate trap/pipework, and the pipework run vs. fall required will be achievable.
8
All connections, pipework/ductwork, etc., can be independently supported and not supported by the unit. The best practice is to install self-supporting brackets prior to the connection of the unit
9
Ensure that all access doors are clear and not blocked from brackets or other services, where required.
10
Check to ensure that all connections kits containing - gaskets, bolts, cleats, screws are available to allow bolting up of the equipment and ancillary equipment.
11
Remove all transport feet and bolts.
12
Check that all required cabling is available for connection[power/controls].
Maintenance/Access
Ref
Inspection/Task
1
There is enough space allowed around and above/below the unit once installed to perform maintenance and remove components. [check the manufacturer's maintenance instructions for requirements]
2
All doors can be fully opened, and panels are removed to gain access to the unit.
3
Check that there is enough space for coils, fans, and filters to be removed and replaced.
4
If the unit is mounted at high level, confirm that there is a safe manner to remove the parts and components and that there is enough space at high level and at the floor level to allow this.
Pre-Commissioning Inspection
Once the equipment has been installed and prior to the functional testing and commissioning phase taking place, the following will be checked.
General
Ref
Inspection/Task
1
Document the information of the unit from its nameplates and cross-reference with the specified information to ensure correct.
2
Ensure the unit is level.
3
All-access doors/panels can be open and closed with no gaps or leakage.
4
Check that all transport bolts and feet are removed.
5
External supply/extract louver, if being used, is installed and fixed with no air gaps.
6
All vibration mounts installed
7
Seismic restraints, where required, installed.
8
Unit and all components, including valves and controls, are labeled in line with the project naming convention.
9
Operation and startup manual for the Fan Coil Unit available.
Electrical General
Ref
Inspection/Task
1
Unit and components are fully earthed in line with the manufacturer's instructions.
2
Earthing has been tested
3
Emergency disconnect installed for each component in line with NFPA/local code requirements
4
Electrical voltage from the site matches the unit required voltages.
5
All cabling is installed and connected on the correct containment/raceways and not damaged.
6
All cabling has been tested/torque tested.
7
A local motor control panel [LMCP] has been installed
8
The local motor control panel has been electrically tested
9
All electrical cabling is labeled in line with the project naming convention.
Controls System/Motorized Dampers & Interlocks
Ref
Inspection/Task
1
Motorized dampers installed as per the drawings and open/close freely.
2
All controls and panels have been installed to operate the motorized dampers
3
Fire trip has been installed and operating/interlocked with the ventilation system.
Fresh Air Supply [Direct]
This will cover Fan Coil Units that are installed connected directly to the outside to draw in the fresh air.
Ref
Inspection/Task
1
The position of the intake louver is in line with the design requirements and positioned so as it will not be affected by any exhaust air.
2
Weather louver/roof cowl installed and weather tight with relevant mesh and is unobstructed.
3
Weather louver installed with correct mesh.
4
Weather louver mesh-free area meets the design requirements
5
Plenum installed connecting the louver to the ducting.
6
Plenum has drain installed with trap to remove any unwanted ingress of water
7
Plenum has access hatch/s installed to allow future maintenance and inspections
8
All fresh air ductwork is installed, correct size, and connected to the unit with correct fixings
9
All attenuators are installed as shown on the drawings.
10
All non-return dampers are installed as per construction drawings.
11
All volume control dampers are installed as per construction drawings.
12
Ductwork insulated and vapor seal in line with the specification.
13
Test holes available in the duct to allow air readings
Fresh Air Supply [AHU]
This will cover Fan Coil Units that are installed connected to an AHU system that supplies its fresh air.
Ref
Inspection/Task
1
The position of ducting is in line with the design requirements.
2
Plenum installed, allowing the connection of the supply ducting to the ducting.
3
All fresh air ductwork is installed, correct size, and connected to the unit with correct fixings
4
All fresh air has been balanced and providing the correct amount of airflow at the required temperature as per design.
5
All attenuators are installed as shown on the drawings.
6
All non-return dampers are installed as per construction drawings.
7
All volume control dampers are installed as per construction drawings.
8
Ductwork insulated and vapor seal in line with the specification.
Check that the fire dampers are installed, as per the drawings, and have been tested in line with the project requirements.
Filters
Ref
Inspection/Task
1
Filter mounting frames are clean and dust-free.
2
Panel filters are installed, clean, and are of the correct grade.
3
Filters have the correct sealing gaskets installed.
4
The filters are not jammed in the rails
5
All components upstream of the filter are clean and dust-free
6
Panel filters are locked in place
7
Differential pressure sensors are installed and calibrated.
Supply Air Fan
Ref
Inspection/Task
1
Electrical connections and cables are complete, fully tested, and torqued in line with project/manufacturer requirements
2
Motor protection installed and operating [Overload]
3
Motor protections calibrated
4
Voltage from electrical systems is correct for the unit requirements [within +/-10%]
5
The fan housing is clean and dust-free
6
Fan, blades, and motors are clean and dust-free.
7
Fan belt tension is correct
8
Fan belt condition is good
9
Check the tightness of fixings [torque]
10
Impeller is balanced
11
Fan/motor rotates in the correct direction with no obstructions [by hand]
12
Fan/motor rotates in the correct direction with no obstructions [electrically bump unit on]
Cooling Coil
Ref
Inspection/Task
1
The cooling coil is clean, in good condition, and the fins undamaged.
2
Ensure that the pipework is the connected and correct size
3
Ensure that the flow and return pipework handings are correct. [Water Inlet downstream of the airflow direction Water Outlet upstream of the airflow direction]
4
The installation of the pipework will not put stress on the equipment connections or create vibrations.
5
The materials used between the equipment and the chilled water system will not cause Electrolysis.
6
Pipework that is to connect to the unit has been weld tested.
7
Pipework that is to connect to the unit has been pressure tested.
8
Pipework that is to connect to the unit has been cleaned and flushed.
9
Equipment has been backflushed.
10
The system has been bled and air removed.
11
The chilled water system has been hydraulically balanced.
12
Pipework is insulated and vapor sealed
13
Insulation is labeled
14
All pressure gauges installed and display scale as per design requirements.
15
All valves/control valves are installed, and the correct direction
16
All commissioning devices are installed
17
All strainers are installed and clean.
Heating Coil
Ref
Inspection/Task
1
The heating coil is clean, in good condition, and the fins are undamaged
2
Ensure that the pipework is the connected and correct size
3
Ensure that the flow and return pipework handings are correct. [Water Inlet downstream of the airflow direction, Water Outlet upstream of the airflow direction]
4
The installation of the pipework will not put stress on the equipment connections or create vibrations.
5
The materials used between the equipment and the heating water system will not cause Electrolysis.
6
Pipework that is to connect to the unit has been weld tested.
7
Pipework that is to connect to the unit has been pressure tested.
8
Pipework that is to connect to the unit has been cleaned and flushed.
9
Equipment has been backflushed.
10
The system has been bled and air removed.
11
The heating water system has been hydraulically balanced.
12
Pipework is insulated and vapor sealed
13
Insulation is labeled
14
All pressure gauges installed and display scale as per design requirements.
15
All valves/control valves are installed and, the correct direction
16
All commissioning devices are installed
17
All strainers are installed and clean.
Refrigerant Dx Coil System
Ref
Inspection/Task
1
The refrigerant coil is clean, in good condition, and fins are undamaged
2
External condenser installed
3
Ensure that the gas and suction pipework is connected and the correct size
4
Ensure that the gas and suction pipework handing's are correct.
5
The installation of the pipework will not put stress on the equipment connections or create vibrations.
6
The materials used between the equipment and the refrigeration pipework system will not cause Electrolysis.
7
Pipework that is to connect to the unit has been pressure/vacuum tested.
8
The system is charged with the correct amount of refrigerant.
9
Pipework is insulated and vapor sealed
10
Insulation is labeled
11
All solenoids installed and operating
12
All sight glasses installed
13
All valves/control valves are installed and, the correct direction
Condensate drain/siphon
Ref
Inspection/Task
1
The condensate is installed to the correct fall.
2
Ensure it is protected from any frost with insulation and/or heating cable.
3
There is a trap installed and is installed in line with manufacturers' requirements. [Check manufacturer's instructions for calculation/requirements]
4
If there are multiple coils installed on a unit, ensure the condensate pipework configuration is installed in line with the manufacturer's requirements.
5
Check that the size of the condensate is correct.
6
Ensure the trap is filled to the correct level.
7
Ensure the drain pan is clean and free of debris
Electric Heater
Ref
Inspection/Task
1
Operation of the heating coil is fan controlled/interlocked
2
Fan delay incorporated into the control's logic, allowing the fan to run [15 mins] after the heater has deactivated/switched off.
3
Heater elements are clean and not obstructed by debris
4
All electrical testing was completed, including torque tests of connections.
5
All safety components are connected and operational, including all thermostats to cut power to the heater if needed.
6
All controls cabling is connected and installed in line with the manufacturers/design drawings.
7
Power is available to the electric heater/control panel for operation.
Supply Air Ductwork
This covers ductwork from the fan coil unit to grilles.
Ref
Inspection/Task
1
All supply air ductwork is installed, correct size, and connected to the unit with correct fixings
2
All attenuators are installed as shown on the drawings.
3
All volume control dampers are installed as per construction drawings.
4
Ductwork insulated and vapor seal in line with the specification.
5
Test holes available in the duct to allow air readings
Return Air Ductwork
Ref
Inspection/Task
1
The position of recirculation grilles is in line with the design requirements and positioned so as will not be affected by the fresh air intake. [Be mindful of short cycling]
2
Plenum installed connecting the grilles to the ducting/fan coil unit.
3
Plenum has access hatch/s installed to allow future maintenance and inspections
4
All extract air ductwork is installed, correct size, and connected to the unit with correct fixings
5
All attenuators are installed as shown on the drawings.
6
All non-return dampers are installed as per construction drawings.
7
All volume control dampers are installed as per construction drawings.
8
Ductwork insulated and vapor seal in line with the specification.
9
Test holes available in the duct to allow air readings
Controls
Ref
Inspection/Task
1
Ensure all sensors and instruments are installed as per the control logic/manufacturers wiring drawings
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional
Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes.The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
We use cookies to enhance your browsing experience and analyze website traffic. By clicking “Accept,” you agree to our use of cookies. You can manage your preferences or withdraw consent at any time. For more information, please review our Privacy Policy.
Functional
Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes.The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.