DATA CENTER | Commissioning Checklist

Last Updated: August 19, 2023, by

A data center commissioning checklist can be used to aid the monitoring and delivery of the activities, tasks, and documentation required to complete an efficient and effective commissioning process of the facility, covering the following:

  • Level 0 – Design & Planning
  • Level 1 – Factory Testing
  • Level 2 – Component Delivery, Installation & Pre-Startup
  • Level 3 – Systems Start-Up
  • Level 4 – Functional Performance Testing
  • Level 5 – Integrated Testing
  • Level 6 – Closeout and Turnover / Handover
🔗 The above Levels have been written and explained more in our article DATA CENTER | 5 Levels Of Commissioning Explained to make it easier and understand what should be delivered at each level.

As noted in the article, the general commissioning process should be based on ASHRAE Guideline 0 – and we cover this process here.

🟩 Level 0- Design & Planning

Level 0, managed by the General Contractor and Owners Commissioning Consultant, serves as the initial stage of the project commissioning process, where the primary focus is on laying the foundation for subsequent stages, evaluating, planning, and documenting the necessary information, tasks, and activities for successful commissioning.

It is important to note that while Level 0 primarily focuses on the below tasks, some will continue throughout the project and carry over into subsequent levels.

StepTask/Activity
L0-01Write and Issue Owners Project Requirements [OPR] Document.
L0-02Oversee Owners Project Requirements [OPR] are being met throughout the contractor design stage, and issue updates to the project team.
L0-03Write and Issue Basis of Design [BOD] Document.
L0-04Ensure that the Basis of Design [BOD] is updated and reviewed by Main Contractor during the 100% design stage, and issue to the project team.
L0-05Develop design [30%, 60%, 90%, 100%] and issue documentation for review and approval.
L0-06Create, Develop, and Issue Computational Fluid Dynamics Study [CFD] Document.
L0-07Complete Commissioning Review of Design [60% to 100% and Issue Report.
L0-08Conduct Short Circuit / Single Point of Failure Coordination Study
L0-09Issue Commissioning Document List covering all stages until handover.
L0-10Write and Issue Data Centre Commissioning Guideline Document.
[This document]
L0-11Agree on Sequencing and Duration of Level 4 & 5 Requirements.
L0-12Issue Initial Integrated and Sequenced Commissioning Programme.
L0-13Issue Commissioning Process Flow Diagram covering all stages until handover.
L0-14Agree Commissioning Process and Responsibility Matrix.
[This document]
L0-15Issue Commissioning Team Organigram covering this stage.
[This is ‘Initial’]
L0-16Agree equipment to be Factory Tested.
L0-17Create, Develop, and Issue Load Bank & Metering Plan for Level 4 & 5 works.
L0-18Write and Issue Initial Commissioning Plan.
L0-19Write and Issue Construction Commissioning Specification.
L0-20Upon contract award, 'Form Commissioning Team' and issue organigram.
L0-21Set up Cx Electronic Platform [Levels 1-6] for later input of commissioning checklists, test procedures and observations/issues.
L0-22Set up and discuss use Document Management System and Numbering Structures for the testing and commissioning works.
L0-23Conduct Commissioning Kick Off meeting.
L0-24Create, Develop, and Issue Commissioning Communication Protocol.
L0-25Create, Develop, and Issue Material Submission Document List.
L0-26Issue Integrated and Sequenced Commissioning Programme.
L0-27Issue Integrated and Sequenced Commissioning Work Logics.
L0-28Agree on method for Capturing Site Issues and Observations.
L0-29Agree on Tagging Process and design of tags to be used.
L0-30Agree on format and content of Factory Testing Scripts.
L0-31Agree on format and content of Factory Testing Reports.
L0-32Plan / programme Factory Testing.
L0-33Agree on format and content of Confirmation to Ship Certificates.
L0-34Agree Training Requirements and Write Training Manual.
L0-35Develop Training Programme.
L0-36Agree on format and content of Pre-Start Up Checklists.
L0-37Agree on format and content of Functional Testing Procedures.
L0-38Agree on format, content, and process for Inviting Owner Team for Witnessing and Verification.
L0-39Agree Final Testing Pack information to be included in O&M.
L0-40Agree on format and content of Daily, Weekly, Monthly Commissioning Reports.
L0-41Agree on format and content of 2 Week Look Ahead Schedule.
L0-42Agree on format and content of Final Commissioning Report.
L0-43Agree on format and content of Systems Manual.
L0-44Agree O&M Requirements.
L0-45Write and Issue Final Commissioning Plan.
L0-46Conduct Commissioning Focused Meetings and Workshops, issuing Minutes.
L0-47Provide to CxP, Commissioning Focused Reports [monthly/weekly].
L0-48Provide to Client, Commissioning Focused Reports [monthly/weekly].
L0-49Review Information for Gap Analysis between Owner Specified Equipment and Main Contractor works.
L0-50Create, Develop, and Issue Electrical Discrimination Study.
L0-51Create, Develop, and Issue Arc Flash Study.
L0-52Agree on Arc Flash Sticker Template to be used.
L0-53Agree Thermal Graphic Inspection locations.
L0-54Create, Develop, and Issue Thermal Graphic Procedure and Plan.
L0-55Create, Develop, and Issue Electrical Lock Out, Tag Out Process and Procedure.
L0-56Create, Develop, and Issue Plant Settings Report.
L0-57Create, Develop, and Issue Schedule of required Work Permits for commissioning activities.
L0-58Create, Develop, and Issue Commissioning Strategies.
L0-59Agree Sequence of Operation [SOO] List.
L0-60Create, Develop, and Issue Sequence of Operations [SOO].
L0-61Create, Develop, and Issue BMS Graphic Document.
L0-62Create, Develop, and Issue BMS Points List Document.
L0-63Create, Develop, and Issue Fire Cause & Effect Matrix.
L0-64Provide to Owner, Level Close Out Reports.
L0-65Sign off Level.
Full Detailed Document
  • Pros:
    • Use Straight Away
    • Insert in Tender Documents
    • Industry Wide Process from Level 0 to Level 6
    • Detailed Responsibility and Roles
    • Includes Commissioning Checklist
  • Description:

    Aimed at anyone who needs a detailed delivery plan and checklist for deploying Commissioning within a Data Center Project, this document is formatted in Microsoft Word/Excel and written so that it can be deployed quickly and easily with minimal updating to suit your specific needs.


    [Once through to the shop there is a sample of the document to view]

Quick Checklist
Buy All Our Documents
  • Pros:
    • 126No. Documents
    • Use Straight Away
    • Amazing Value
  • Description:

    We have been asked several times to create a complete document package covering everything we have uploaded to the site.

    So it's taken some time, but here it is....126No. Documents for you to download in Microsoft Word, Microsoft Excel & PDF Formats.

    CLICK THE BUY HERE TO SEE/DOWNLOAD A FULL LIST OF DOCUMENTS INCLUDED...


Full Detailed Document
Pros:
  • Use Straight Away
  • Insert in Tender Documents
  • Industry Wide Process from Level 0 to Level 6
  • Detailed Responsibility and Roles
  • Includes Commissioning Checklist
Description:

Aimed at anyone who needs a detailed delivery plan and checklist for deploying Commissioning within a Data Center Project, this document is formatted in Microsoft Word/Excel and written so that it can be deployed quickly and easily with minimal updating to suit your specific needs.


[Once through to the shop there is a sample of the document to view]

Quick Checklist
Pros:
  • Easy
  • Quick
  • High Level
  • Tracker
Description:

Here is our open copy [MS Word] & [MS Excel] of the Data Center Commissioning Checklist, for making life a little easier...

Buy All Our Documents
Pros:
  • 126No. Documents
  • Use Straight Away
  • Amazing Value
Description:

We have been asked several times to create a complete document package covering everything we have uploaded to the site.

So it's taken some time, but here it is....126No. Documents for you to download in Microsoft Word, Microsoft Excel & PDF Formats.

CLICK THE BUY HERE TO SEE/DOWNLOAD A FULL LIST OF DOCUMENTS INCLUDED...


🟩 Level 1 – Factory Testing

Level 1, managed by the General Contractor, is where a diverse range of roles and responsibilities come together from the commissioning team to ensure that the selected plant and equipment is factory tested.

Although this stage is relatively short and uncomplicated, it necessitates the dedicated efforts of individuals with specialized tasks and expertise.

StepTask/Activity
L1-01Fix and confirm dates of Factory Testing.
L1-02Create, Develop, and Issue Factory Testing Scripts.
L1-03Conduct Commissioning Focused Meetings and Workshops, where required.
L1-04Organize Transportation and Accommodation for Factory Testing.
L1-05Conduct Factory Acceptance Testing with owner team at factory or remotely.
L1-06Add any issues to Observation Register and managing to close.
L1-07Create, Develop, and Issue Factory Testing Reports for all equipment.
L1-08Obtain and Issue Factory QA/QC documents for record and filing.
L1-09File and manage Factory Testing information and records within the Project electronic filing system.
L1-10Install all Red Tags where applicable.
L1-11Issue Confirmation to Ship Certificate.
L1-12Ship equipment to site.
L1-13Provide to Owner, Level Close Out Reports.
L1-14Sign off Level.

🟩 Level 2 – Component Delivery, Installation & Pre-Startup

Level 2, managed by the General Contractor, is a crucial stage in the data center commissioning process, ensuring that all equipment, plant, and components are successfully delivered, installed, and thoroughly checked via pre-start-up activities to meet the project requirements.

This stage sets the foundation for the subsequent energization phase at Level 3.

StepTask/Activity
L2-01Write and Issue Level 2 Checklists and Scripts that will be used to facilitate the works.
L2-02Plan and Manage Deliveries of plant, equipment, and materials.
[If not, Factory Tested]
L2-03Complete Delivery and Storage Checklists when plant, equipment and materials arrive on site.
L2-04Complete Installation Checklist Inspections.
L2-05Complete Pre-Start-up / Energization Inspections.
L2-06Conduct any First of Kind [FOK] Inspections if noted in the project process with the owner’s CxP.
L2-07For Electrical Panels ensure Arc Flash Stickers are attached and Breakers Set in line with the Arc Flash Report and Discrimination Study.
L2-08Complete Foreign Object Detection [FOD] Inspection for all electrical panels and equipment.
L2-09Update Commissioning Tracking to reflect actual status and progress.
[Manually or as per Commissioning Electronic Platform]
L2-10Manage the Overall Programme for the Commissioning Tasks and Activities.
L2-11Add any issues to Observation Register and managing to close.
L2-12File and manage documentation and records within the Project electronic filing system.
L2-13Issue regular 2 Week Look Ahead Schedules for Commissioning Team Resource Planning.
L2-14Conduct Daily Morning Coordination Workshop.
L2-15Provide Daily Commissioning Updates.
L2-16Conduct Commissioning Focused Weekly Meetings and Workshops.
L2-17Provide Commissioning Focused Reports.
[Monthly / Weekly]
L2-18Install all Yellow Tags where applicable.
L2-19Provide to Owner, Level Close Out Reports.
L2-20Sign off Level.

🟩 Level 3 – Systems Start-Up

Level 3, managed by the General Contractor, encompasses tasks and activities to ensure that the individual plant, equipment, systems, and components are successfully started up, tested, and operating per the design intent and approved testing scripts/procedures.

This stage is crucial before combining the different systems for Level 4 and Level 5 works.

StepTask/Activity
L3-01Write and Issue Scripts/Start-up Plans that will be used to facilitate the start-up and testing works.
L3-02Write and Issue Work Permits as noted in Level 0 that will be used to facilitate the start-up and functional testing works.
L3-03Install Temporary Equipment and Instruments to facilitate the testing and Level 4 Works in line with the Load Bank & Equipment Plan.
L3-04Ensure BMS and Control Logics are ready and available.
[Point to Graphic]
L3-05Ensure Control Room and equipment is ready and available, for testing to commence.
L3-06Plan and Manage Energization, Site Testing and Acceptance of plant, equipment, and materials in line with approved procedures, scripts, and programme.
L3-07Conduct any First of Kind [FOK] Testing if noted in the project process with the Owner’s Commissioning Consultant.
L3-08Update Commissioning Tracking to reflect actual status and progress.
[Manually or as per Commissioning Electronic Platform]
L3-09Manage the Overall Programme for the Commissioning Tasks and Activities.
L3-10Add any issues to Observation Register and managing to close.
L3-11File and manage documentation and records within the Project electronic filing system.
L3-12Issue regular 2 Week Look Ahead Schedules for Commissioning Team Resource Planning.
L3-13Conduct Daily Morning Coordination Workshop.
L3-14Provide Daily Commissioning Updates.
L3-15Conduct Commissioning Focused Weekly Meetings and Workshops.
L3-16Provide Commissioning Focused Reports
[Monthly / Weekly]
L3-17Issue Operation and Maintenance Manuals.
L3-18Complete Clean of Data Halls and critical areas.
L3-19Install all Green Tags where applicable.
L3-20Provide to Owner, Level Close Out Reports.
L3-21Sign off Level.

🟩 Level 4 – Functional Performance Testing

Level 4, managed and delivered by the Owners Commissioning Consultant, with support from the General Contractor, focuses on bringing the systems together, integrating them, and conducting a series of rigorous tests to ensure their alignment with the Owner’s Project Requirements [OPR], Basis of Design [BOD], and relevant contract documentation such as drawings, specifications, and control logics.

This stage plays a pivotal role in verifying the functional performance of these integrated systems.

StepTask/Activity
L4-01Write and Issue Scripts that will be used to facilitate the testing works.
L4-02Write and Issue Work Permits as noted in Level 0 that will be used to facilitate the works.
L4-03Ensure that Temporary Equipment and Instruments are installed in line with the approved Load Bank & Equipment Plan as noted in Level 0 works.
L4-04Operate Temporary Equipment and Instruments to facilitate the testing works.
L4-05Plan and Manage Testing and Acceptance of plant, equipment, and systems in line with approved procedures, scripts, and programme.
L4-06Complete Thermographic Studies and create report as noted in Level 0 works.
L4-07Download Data and Information for review after testing.
L4-08Update Commissioning Tracking to reflect actual status and progress.
[Manually or as per Commissioning Electronic Platform]
L4-09Add any issues to Observation Register and managing to close.
L4-10File and manage documentation and records within the Project electronic filing system
L4-11Issue regular 2 Week Look Ahead Schedules for Commissioning Team Resource Planning.
L4-12Conduct Daily Morning Coordination Workshop.
L4-13Provide Daily Commissioning Updates.
L4-14Conduct Commissioning Focused Weekly Meetings and Workshops.
L4-15Provide Commissioning Focused Reports.
[Level 4 / Monthly / Weekly]
L4-16Issue Final Operation and Maintenance Manuals.
L4-17Start Facility Operatives Training in line with the documents noted in Level 0 works.
L4-18Install all Blue Tags where applicable.
L4-19Provide to Owner, Level Close Out Reports.
L4-20Sign off Level.
Data Center Commissioning Checklist [MS Word] & [MS Excel]

Here is our open copy [MS Word] & [MS Excel] of the Data Center Commissioning Checklist, for making life a little easier...

#CC: 066
Buy Here | $1.99

🟩 Level 5 – Integrated Testing

The Level 5 Integrated Testing phase, managed by the Owners Commissioning Consultant, with support from the General/Main Contractor, is the final step in validating the performance of the installed systems.

It focuses on integrating all the systems, conducting rigorous tests to evaluate and verify their functionality, interoperation, and response to simulated failure scenarios, demonstrating that they operate seamlessly together, in accordance with the owner’s project requirements [OPR], Basis of Design [BOD], and other contractual documentation such as drawings, specifications, and control logics.

Once the testing has been completed, data will be collected and analyzed from the systems and instruments systems to ensure that critical data hall and other space ambient conditions are maintained during different testing scenarios.

StepTask/Activity
L5-01Write and Issue Scripts that will be used to facilitate the testing works.
L5-02Write and Issue Work Permits as noted in Level 0 that will be used to facilitate the works.
L5-03Ensure that Temporary Equipment and Instruments are installed in line with the approved Load Bank & Equipment Plan as noted in Level 0 works.
L5-04Operate Temporary Equipment and Instruments to facilitate the testing works.
L5-05Plan and Manage Testing and Acceptance of plant, equipment, and systems in line with approved procedures, scripts, and programme.
L5-06Download Data and Information for review after testing.
L5-07Remove Temporary Equipment after testing has been agreed complete.
L5-08Update Commissioning Tracking to reflect actual status and progress.
[Manually or as per Commissioning Electronic Platform]
L5-09Add any issues to Observation Register and managing to close.
L5-10File and manage documentation and records within the Project electronic filing system.
L5-11Issue regular 2 Week Look Ahead Schedules for Commissioning Team Resource Planning.
L5-12Conduct Daily Morning Coordination Workshop.
L5-13Provide Daily Commissioning Updates.
L5-14Conduct Commissioning Focused Weekly Meetings and Workshops.
L5-15Provide Commissioning Focused Reports.
[Level 5 / Monthly / Weekly]
L5-16Complete Facility Operatives Training in line with the documents noted in Level 0 works.
L5-17Install all White Tags where applicable.
L5-18Provide to Owner, Level Close Out Reports.
L5-19Sign off Level.

🟩 Level 6 – Closeout/Handover

Managed and executed by the Owners Commissioning Consultant, with the support of the General Contractor, Level 6 is the final stage, where the Commissioning Process is completed with the systems transitioning to the Owner and Facilities Team, ensuring that the data center is fully prepared and optimized for operation, and all commissioning-related activities are concluded in a systematic and well-documented manner.

StepTask/Activity
L6-01Write and Issue Closeout Script.
L6-02Complete Clean of Data Halls and critical areas.
[If not completed under Level 3 tasks and activities]
L6-03Conduct Final Site Inspection.
L6-04Inspect and Document all Plant Settings.
L6-05Conduct Lessons Learned Workshop and document.
L6-06Ensure all Issues and Observations have been closed out for the project.
L6-07Ensure all Commissioning Documentation is complete and uploaded to the relevant electronic platforms.
L6-08Conduct Closeout Meeting.
L6-09Issue Final Commissioning Report.
L6-10Write and Issue Systems Manual.
L6-11Provide to Owner, Level Close Out Reports.
L6-12Sign off Level.

⬜ Data Center Commissioning Checklist [Downloads]

Below we have included our Excel & MS Word Data Center Commissioning Checklists that can be viewed and purchased from our shop by clicking the button below. You will receive each type of checklist [.doc] & [.xls] shown within the purchase.

⬜ Data Center Commissioning Checklist [MS Word]

⬜ Data Center Commissioning Checklist [MS Excel]


⬛ Related Articles

⬛ Latest Articles


⬛ Author

If you would like to know more about the author, here is my Personal Linkedin Account